Timing changes present value. R20,000 now; R30,000 in year 3; R50,000 in year 5; r = 5%.

00:00:01.000 --> 00:00:07.000
MATHEMATICS · define the relationship and the meaning of each symbol before calculating.

00:00:07.000 --> 00:00:14.000
Ct: payment at year t (rand); r = 0.05 per year. Payments: R20,000 at year 0; R30,000 at year 3; R50,000 at year 5.

00:00:14.000 --> 00:00:23.000
INPUT · undiscounted payments · read the axis units and the numerical values.

00:00:23.000 --> 00:00:27.000
R20,000 now; R30,000 in year 3; R50,000 in year 5; r = 5%.

00:00:27.000 --> 00:00:33.700
Year 0: R20,000 / 1.05^0 = R20,000.00. Running present value = R20,000.00.

00:00:33.700 --> 00:00:40.400
Year 3: R30,000 / 1.05^3 = R25,915.13. Running present value = R45,915.13.

00:00:40.400 --> 00:00:43.100
Year 5: R50,000 / 1.05^5 = R39,176.31. Running present value = R85,091.44.

00:00:43.100 --> 00:00:52.100
OUTPUT · discounted contributions · read the axis units and the numerical values.

00:00:52.100 --> 00:00:59.100
R20,000 + R25,915.13 + R39,176.31 = R85,091.44. Later costs receive smaller present-value factors.

00:00:59.100 --> 00:01:05.100
CALCULATION · substitute the defined inputs; keep units through each intermediate step.

00:01:05.100 --> 00:01:08.100
Year zero: 20,000 × 1 = 20,000 R present value

00:01:08.100 --> 00:01:11.100
Year three: 30,000 / 1.05³ = 25,915.127956 R present value

00:01:11.100 --> 00:01:14.100
Year five: 50,000 / 1.05⁵ = 39,176.308323 R present value

00:01:14.100 --> 00:01:17.100
Total: 20,000 + 25,915.127956 + 39,176.308323 = 85,091.436279 R present value

00:01:17.100 --> 00:01:26.500
SENSITIVITY · change one declared input · read the axis units and the numerical values.

00:01:26.500 --> 00:01:29.900
Rate 0%: 100000 R present value. Same dated cost stream; change the annual discount rate only.

00:01:29.900 --> 00:01:33.300
Rate 5%: 85091.4 R present value. Same dated cost stream; change the annual discount rate only.

00:01:33.300 --> 00:01:36.300
Rate 10%: 73585.5 R present value. Same dated cost stream; change the annual discount rate only.

00:01:36.300 --> 00:01:42.300
Check: At r = 0 the total must equal R100,000. Year-zero cost must remain R20,000 for every rate. Compare independent term-by-term calculations, retaining unrounded values until the final displayed total.

00:01:42.300 --> 00:02:00.300
ONE ROW · The same invoice can occupy very different places in a present-value comparison.

00:02:00.300 --> 00:02:10.300
PARAMETER MAP · 7381 evaluated cells. The colour limits stay fixed across every row.

00:02:10.300 --> 00:02:21.383
Every cell discounts a single R50,000 payment. At year zero all rates meet at R50,000. At zero discount rate every date has the same present value. Moving away from those

00:02:21.383 --> 00:02:31.008
boundaries reveals the interaction between timing and rate. A programme total adds the individual discounted payments; this surface is one term, not a full option appraisal.

00:02:31.008 --> 00:02:43.008
VALUE LANDSCAPE · Height and colour encode Present value (R). This is a graph over the two input axes, not automatically a physical pavement shape.

00:02:43.008 --> 00:02:51.425
Scenario rates and a constant stated payment, not recommended appraisal rates. Use a consistent real or nominal price basis before comparing alternatives.

00:02:51.425 --> 00:02:56.792
Consistent price basis and rate are assumed; this is not a treatment recommendation.